Dematic Electromechanical Systems Middle East LLC, Dubai
EPIC Project:
The GCC's Largest Fully Automated Distribution Centre (O-Mega DC) of Land Mark group in Jebel Ali
Free Zone, Dubai, UAE.
* Tallest High Bay Structure at 43 Meters.
* Ability to handle Pallet carton pieces and Garments on Hangers interchangeably.
* A new Era of Supply Chain.
* 10 Automated and 3 Manual Docks can receive 230-foot units per day.
* Storage for 2.2 Million Cartons and 2 Million Garments on Hanger (GOH).
* 1200 Robotic Multi-shuttles.
* Handling up to 250,000 Garments on Hanger every day.
* High Bay Warehouse with Automated Pallet.
* Handling first in the region to use Hypoxic Fire prevention system.
Project Value: Euro 135 Million
Key responsibilities
* Develop fully integrated Project Schedule as defined in the contract in consultation with Project
Director and Package Managers.
* Discuss with various stake holders (Engineering, Procurement, Manufacturing, Installation,
commissioning etc.) and finalize the baseline schedule.
* Responsible for Collecting the status of various aspects of project progress i.e., Engineering,
procurement, Installation and Commissioning and update schedule and generate weekly, monthly reports
to internal and external stakeholders.
* Draft, Evaluate, Negotiate and Execute contracts of Vendor and Sub contractors.
* Delay analysis and mitigations.
* Preparation of Extension of time claims and prolongation cost and submission.
* Communicated with client and other stakeholders for any contractual matters.
* Manage record keeping for all contract-related correspondence and documentation.
* Monitor, track, identify trends, predict and report project status.
* Review, produce and document cost accounting data and reports project management trends.
* Attend Monthly risk review, Internal weekly progress and external progress review meetings.