* Largest Public Sector PPM implementation in the world - initial implementation on SAP PPM 5.0
* Activities performed:
* Blueprint and design during which multiple WRICEF (Workflow, Reports, Interfaces,
Conversion, Enhancements and Forms) were identified. Involvement related to:
* Requirements gathering
* Creation of functional specifications
* Testing (including UAT)
Most notably the following was designed and delivered in respect of the initial delivery
* Enhanced Planning application catering for high level as well as Fund Source level
planning across multiple Items (Projects)
* Baselining and approval application
* Enhanced Governance mechanism to capture checklist Items, dates, phase status,
decision point (gate) maintenance and document linking
* Complex conversion and data migration tools for existing PS master and transactional
data
* PS integration and support
* End user training
* Documentation
* Support
* Continuous improvement and additional requirements added after the initial phase included
multiple additional technical and functional enhancements.