Functions: Define and execute project continuation strategy, including financing modality, contracting of services to take over of the project
procurement and pending works
Construction Manager (Morichal Engineering, procurement and construction for the expansion of production from 105
Position: area) Project: to 165MBD of extra heavy crude oil at the facilities of the Sinovensa Oil Company
(Jan2014-Nov2017)
Functions: Responsible for the construction of the following activities.
Earthworks for the Flow Station - Morichal, Manufacture of tanks for diluted wet oil 02x150MBLS and for diluent 01x50MBLS - Morichal, Manufacture
of 1,750,000 kg of piperack for the flow station, Construction of the diluted wet crude oil pumping system located in storage yard of Diluente -
Morichal, Construction of 26 kilometers of Diluenducto 12 "- Morichal. , Construction of 7 kilometers of 10 "pipe for injection water - Morichal."